Case Study 3

Example of DAQ (Data Acquisition System) resources allocation for an Automated PCBA Functional Test Fixture:

PCBA TPTypeResourceRangeUnit
Test Point 1DigitalNI-6229 I/O 390.0 – 3.3 Volts
Test Point 2AnalogNI-6229 I/O 160.0 – 2.5Volts
Test Point 3AnalogNI-6229 I/O 170.0 – 10.0Volts
Test Point 4AnalogNI-6229 I/O 180.0 – 5.0Volts
Signals to be connected to PXI Chassis